nerdexam
PMIPMI

PMI-RMP · Question #171

PMI-RMP Question #171: Real Exam Question with Answer & Explanation

The correct answer is D: Determines if the project constraints are still valid. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

In addition to monitoring and controlling the project risks for their status and information the risk monitoring and controlling process accomplishes four key things for a project. Which one of the following is NOT a determination that is made by the risk monitoring and controlling process?

Options

  • ADetermines if the project assumptions are still valid
  • BDetermines if the risk management policies and procedures are being followed
  • CDetermines if the risk contingency reserves should be modified to be in alignment with the current risk
  • DDetermines if the project constraints are still valid

Topics

#Risk Monitoring and Control Process#Project Assumptions#Contingency Reserves#Risk Management Effectiveness

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions