PMIPMI
PMI-RMP · Question #171
PMI-RMP Question #171: Real Exam Question with Answer & Explanation
The correct answer is D: Determines if the project constraints are still valid. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
In addition to monitoring and controlling the project risks for their status and information the risk monitoring and controlling process accomplishes four key things for a project. Which one of the following is NOT a determination that is made by the risk monitoring and controlling process?
Options
- ADetermines if the project assumptions are still valid
- BDetermines if the risk management policies and procedures are being followed
- CDetermines if the risk contingency reserves should be modified to be in alignment with the current risk
- DDetermines if the project constraints are still valid
Topics
#Risk Monitoring and Control Process#Project Assumptions#Contingency Reserves#Risk Management Effectiveness
Community Discussion
No community discussion yet for this question.