PMIPMI
PMI-RMP · Question #162
PMI-RMP Question #162: Real Exam Question with Answer & Explanation
The correct answer is A: Quantitative risk analysis is the process of numerically analyzing the effect of identified risks on. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
You are the project manager for your organization. You are preparing for the quantitative risk analysis. Mark, a project team member, wants to know why you need to do quantitative risk analysis when you just completed qualitative risk analysis. Which one of the following statements best defines what quantitative risk analysis is?
Options
- AQuantitative risk analysis is the process of numerically analyzing the effect of identified risks on
- BQuantitative risk analysis is the planning and quantification of risk responses based on probability
- CQuantitative risk analysis is the review of the risk events with the high probability and the highest
- DQuantitative risk analysis is the process of prioritizing risks for further analysis or action by assessing
Topics
#Quantitative Risk Analysis#Risk Analysis Definition#Project Risk Management#Risk Process
Community Discussion
No community discussion yet for this question.