nerdexam
PMI

PMI-RMP · Question #161

Marsha is the project manager of the NHQ Project. There's a risk that her project team has identified, which could cause the project to be late by more than a month. Marsha does not want this risk eve

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #161. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

Marsha is the project manager of the NHQ Project. There's a risk that her project team has identified, which could cause the project to be late by more than a month. Marsha does not want this risk event to happen so she devises extra project activities to ensure that the risk event will not happen. The extra steps, however, will cost the project an additional $10,000. What type of risk response is this approach?

Options

  • AEnhancing
  • BExploiting
  • CMitigation
  • DTransference

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Mitigation#Risk response strategies#Threat response#Risk management process
Full PMI-RMP Practice