PMI-ACP · Question #738

An agile team delivered a feature in the last iteration. The product owner, who missed the planning and review meetings, was dissatisfied with the feature. The team conducted a retrospective and…

The correct answer is A. Ensure that the product owner reviews the acceptance criteria for delivered user stories. The core issue is that the product owner missed both the planning and review meetings and was then dissatisfied with the output. This signals a breakdown in acceptance criteria validation. The correct next step is to ensure the product owner reviews and agrees to the acceptance…

Submitted by zhang_li· Apr 18, 2026Stakeholder Engagement

Question

An agile team delivered a feature in the last iteration. The product owner, who missed the planning and review meetings, was dissatisfied with the feature. The team conducted a retrospective and reviewed the user stories related it. What should the agile team do next?

Options

  • AEnsure that the product owner reviews the acceptance criteria for delivered user stories.
  • BAugment the quality assurance and continuous integration processes for delivery.
  • CApproach the relevant developers and testers regarding quality issues in upcoming iterations.
  • DAsk the product owner to define the entire scope of delivery two to three iterations in advance.

How the community answered

(57 responses)
  • A
    72% (41)
  • B
    4% (2)
  • C
    7% (4)
  • D
    18% (10)

Explanation

The core issue is that the product owner missed both the planning and review meetings and was then dissatisfied with the output. This signals a breakdown in acceptance criteria validation. The correct next step is to ensure the product owner reviews and agrees to the acceptance criteria for delivered user stories-this prevents future misalignment between what was built and what the PO expected. Option B addresses process quality but not the root cause. Option C targets developers/testers but the problem stems from unclear requirements and absent PO engagement. Option D (locking scope 2-3 iterations ahead) is contrary to agile's adaptive nature.

Topics

#Product Owner#Acceptance Criteria#Stakeholder Engagement#Continuous Improvement