PMI-ACP · Question #700

A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?

The correct answer is D. Iteration burndown chart. An iteration (sprint) burndown chart shows the amount of work remaining day-by-day within a sprint, making it ideal for communicating daily resource utilization and activity progress to stakeholders. It is updated daily and reflects both planned work and actual progress at the…

Submitted by joshua94· Apr 18, 2026Stakeholder Engagement

Question

A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?

Options

  • AShared vision statement and sprint goal
  • BRelease burnup chart
  • CVelocity metrics
  • DIteration burndown chart

How the community answered

(58 responses)
  • A
    10% (6)
  • B
    2% (1)
  • C
    7% (4)
  • D
    81% (47)

Explanation

An iteration (sprint) burndown chart shows the amount of work remaining day-by-day within a sprint, making it ideal for communicating daily resource utilization and activity progress to stakeholders. It is updated daily and reflects both planned work and actual progress at the task level. A shared vision/sprint goal (A) is directional, not a status tool. A release burnup chart (B) shows cumulative progress over the entire release, not daily sprint activity. Velocity metrics (C) are sprint-over-sprint historical averages, not a daily activity view.

Topics

#Scrum Master responsibilities#Agile reporting tools#Iteration burndown chart#Stakeholder communication