PMI-ACP · Question #699

PMI-ACP Question #699: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #699. The question stem and answer options stay visible for context.

Submitted by kim_seoul· Apr 18, 2026Stakeholder Engagement

Question

A team is delivering work as per the sprint plan, and team velocity is stabilized. However, at the end of the release, the customer is dissatisfied with project quality. What should the agile project manager have done to avoid this?

Options

  • AInvited end customers to attend the stand ups
  • BOrganized design review sessions with the customer to obtain sign-off
  • CHeld regular meetings with the product owner and project team to elicit detailed business
  • DConducted frequent review meetings with the customer to continually enhance delivery

Unlock PMI-ACP to see the answer

You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Customer feedback#Sprint reviews#Continuous improvement#Stakeholder collaboration
Full PMI-ACP PracticeBrowse All PMI-ACP Questions