A quality control team identified multiple defects in a work product. The team's analysis traced the defects to the on-site junior-level engineer. For the project manager to get to the root cause…

The correct answer is B. Retrospective. A Retrospective (B) is a structured, formal meeting where the team looks backward at completed work to examine what went well, what went wrong, and - most importantly - why. It is the correct forum for root-cause analysis because it creates a safe, structured environment to dig…

Tools and documentation

Question

A quality control team identified multiple defects in a work product. The team's analysis traced the defects to the on-site junior-level engineer. For the project manager to get to the root cause, which of the following meeting types should the manager conduct?

Options

  • AStand-up
  • BRetrospective
  • CKickoff
  • DFace-to-face

How the community answered

(40 responses)
  • A
    8% (3)
  • B
    78% (31)
  • C
    3% (1)
  • D
    13% (5)

Explanation

A Retrospective (B) is a structured, formal meeting where the team looks backward at completed work to examine what went well, what went wrong, and - most importantly - why. It is the correct forum for root-cause analysis because it creates a safe, structured environment to dig into process failures, skill gaps, or miscommunications that produced the defects. A Stand-up (A) is a brief daily status check, not an analytical session. A Kickoff (C) occurs at the project's start and sets expectations, not diagnose past failures. A Face-to-face (D) describes a meeting format or modality, not a specific meeting type with a defined purpose for root-cause investigation.

Topics

#retrospective#root cause analysis#quality control#meeting types