The correct answer is B: Project name. The project charter is the foundational authorization document that formally establishes a project's existence and grants the project manager authority to apply resources. It must include the Project Name (B) as the unique identifier and the Purpose (E) - the business justificati

Question

A project sponsor asks a project manager to create a project charter. Which of the following should be included in the project charter? (Choose two.)

Options

  • ALessons learned
  • BProject name
  • CImpact analysis
  • DRisk log
  • EPurpose
  • FTeam members
  • GMilestones

Explanation

The project charter is the foundational authorization document that formally establishes a project's existence and grants the project manager authority to apply resources. It must include the Project Name (B) as the unique identifier and the Purpose (E) - the business justification and objectives that explain why the project exists. Lessons Learned (A) are historical inputs used to inform planning, not charter content. Impact Analysis (C) is a change management artifact. A Risk Log (D) is a living tracking document developed during planning. Team Members (F) are identified later during resource planning. Milestones (G) at a high level can appear in a charter, but Purpose and Project Name are far more fundamental and definitional components.