A project sponsor asks a project manager to create a project charter. Which of the following should be included in the project charter? (Choose two.)

The correct answer is B. Project name E. Purpose. The project charter is the foundational authorization document that formally establishes a project's existence and grants the project manager authority to apply resources. It must include the Project Name (B) as the unique identifier and the Purpose (E) - the business…

Tools and documentation

Question

A project sponsor asks a project manager to create a project charter. Which of the following should be included in the project charter? (Choose two.)

Options

  • ALessons learned
  • BProject name
  • CImpact analysis
  • DRisk log
  • EPurpose
  • FTeam members
  • GMilestones

How the community answered

(22 responses)
  • B
    86% (19)
  • C
    9% (2)
  • F
    5% (1)

Explanation

The project charter is the foundational authorization document that formally establishes a project's existence and grants the project manager authority to apply resources. It must include the Project Name (B) as the unique identifier and the Purpose (E) - the business justification and objectives that explain why the project exists. Lessons Learned (A) are historical inputs used to inform planning, not charter content. Impact Analysis (C) is a change management artifact. A Risk Log (D) is a living tracking document developed during planning. Team Members (F) are identified later during resource planning. Milestones (G) at a high level can appear in a charter, but Purpose and Project Name are far more fundamental and definitional components.

Topics

#project charter#project initiation#project name#purpose