PK0-004 · Question #983
PK0-004 Question #983: Real Exam Question with Answer & Explanation
The correct answer is B: Project name. The project charter is the foundational authorization document that formally establishes a project's existence and grants the project manager authority to apply resources. It must include the Project Name (B) as the unique identifier and the Purpose (E) - the business justificati
Question
Options
- ALessons learned
- BProject name
- CImpact analysis
- DRisk log
- EPurpose
- FTeam members
- GMilestones
Explanation
The project charter is the foundational authorization document that formally establishes a project's existence and grants the project manager authority to apply resources. It must include the Project Name (B) as the unique identifier and the Purpose (E) - the business justification and objectives that explain why the project exists. Lessons Learned (A) are historical inputs used to inform planning, not charter content. Impact Analysis (C) is a change management artifact. A Risk Log (D) is a living tracking document developed during planning. Team Members (F) are identified later during resource planning. Milestones (G) at a high level can appear in a charter, but Purpose and Project Name are far more fundamental and definitional components.
Community Discussion
No community discussion yet for this question.