PK0-004 · Question #978
Which of the following occur during the initiation phase of a project? (Choose two.)
The correct answer is A. The project charter is created. D. A high-level timeline is estimated. The initiation phase focuses on formally authorizing the project and establishing its high-level parameters. The project charter (A) is the primary deliverable of initiation - it formally authorizes the project, names the project manager, and outlines high-level scope…
Question
Which of the following occur during the initiation phase of a project? (Choose two.)
Options
- AThe project charter is created.
- BA detailed project plan is available.
- CDetailed risk responses are documented.
- DA high-level timeline is estimated.
- ELessons learned are documented.
How the community answered
(24 responses)- A96% (23)
- B4% (1)
Explanation
The initiation phase focuses on formally authorizing the project and establishing its high-level parameters. The project charter (A) is the primary deliverable of initiation - it formally authorizes the project, names the project manager, and outlines high-level scope, objectives, and stakeholders. A high-level timeline (D) is also estimated during initiation to give stakeholders a rough sense of duration before detailed planning begins. A detailed project plan (B) and detailed risk responses (C) are products of the planning phase, not initiation. Lessons learned (E) are documented during the closing phase.