Which of the following occur during the initiation phase of a project? (Choose two.)

The correct answer is A. The project charter is created. D. A high-level timeline is estimated. The initiation phase focuses on formally authorizing the project and establishing its high-level parameters. The project charter (A) is the primary deliverable of initiation - it formally authorizes the project, names the project manager, and outlines high-level scope…

Project life cycle phases

Question

Which of the following occur during the initiation phase of a project? (Choose two.)

Options

  • AThe project charter is created.
  • BA detailed project plan is available.
  • CDetailed risk responses are documented.
  • DA high-level timeline is estimated.
  • ELessons learned are documented.

How the community answered

(24 responses)
  • A
    96% (23)
  • B
    4% (1)

Explanation

The initiation phase focuses on formally authorizing the project and establishing its high-level parameters. The project charter (A) is the primary deliverable of initiation - it formally authorizes the project, names the project manager, and outlines high-level scope, objectives, and stakeholders. A high-level timeline (D) is also estimated during initiation to give stakeholders a rough sense of duration before detailed planning begins. A detailed project plan (B) and detailed risk responses (C) are products of the planning phase, not initiation. Lessons learned (E) are documented during the closing phase.

Topics

#project initiation#project charter#high-level timeline#initiation activities