A project team member in a balanced matrix organization has been underperforming. Which of the following steps should the project manager take FIRST to correct the team member's performance?
The correct answer is A. Conduct a face-to-face discussion with the team member. In a balanced matrix organization, the project manager shares authority with the functional manager. The appropriate first step when addressing underperformance is always a direct, private conversation with the team member. This gives the individual an opportunity to understand…
Question
A project team member in a balanced matrix organization has been underperforming. Which of the following steps should the project manager take FIRST to correct the team member's performance?
Options
- AConduct a face-to-face discussion with the team member.
- BDraft a formal memo to the functional manager.
- CSend a group email to the project team encouraging hard work.
- DInitiate a performance improvement plan.
How the community answered
(25 responses)- A72% (18)
- B8% (2)
- C4% (1)
- D16% (4)
Explanation
In a balanced matrix organization, the project manager shares authority with the functional manager. The appropriate first step when addressing underperformance is always a direct, private conversation with the team member. This gives the individual an opportunity to understand expectations, explain any obstacles, and improve without formal escalation. Drafting a memo to the functional manager (B) or initiating a performance improvement plan (D) are escalation steps that should only follow a direct discussion. A group email (C) is inappropriate as it singles out an individual indirectly and publicly, which is both ineffective and unprofessional.