The correct answer is B: Task. A Work Breakdown Structure (WBS) decomposes the total project scope into manageable components. Tasks (B) are the work packages - the lowest-level deliverable elements in the WBS. Duration (D) is associated with each task to indicate how long each work package will take, supporti
Question
Options
- AProgram
- BTask
- CProject
- DDuration
- ECost variance
- FStatement of work
Explanation
A Work Breakdown Structure (WBS) decomposes the total project scope into manageable components. Tasks (B) are the work packages - the lowest-level deliverable elements in the WBS. Duration (D) is associated with each task to indicate how long each work package will take, supporting schedule development. A Program (A) is a collection of related projects - not a WBS component. Cost variance (E) is a performance metric, not a WBS element. Statement of work (F) is a procurement/contract document. Project (C) refers to the overall endeavor, not a WBS element within it.
Community Discussion
No community discussion yet for this question.