nerdexam
CompTIA

PK0-004 · Question #948

The project sponsor has asked a new project manager to create a WBS to present at the quarterly meeting with shareholders. Which of the following should be included in the WBS? (Choose two.)

The correct answer is B. Task D. Duration. A Work Breakdown Structure (WBS) decomposes the total project scope into manageable components. Tasks (B) are the work packages - the lowest-level deliverable elements in the WBS. Duration (D) is associated with each task to indicate how long each work package will take…

Tools and documentation

Question

The project sponsor has asked a new project manager to create a WBS to present at the quarterly meeting with shareholders. Which of the following should be included in the WBS? (Choose two.)

Options

  • AProgram
  • BTask
  • CProject
  • DDuration
  • ECost variance
  • FStatement of work

How the community answered

(42 responses)
  • A
    2% (1)
  • B
    95% (40)
  • C
    2% (1)

Explanation

A Work Breakdown Structure (WBS) decomposes the total project scope into manageable components. Tasks (B) are the work packages - the lowest-level deliverable elements in the WBS. Duration (D) is associated with each task to indicate how long each work package will take, supporting schedule development. A Program (A) is a collection of related projects - not a WBS component. Cost variance (E) is a performance metric, not a WBS element. Statement of work (F) is a procurement/contract document. Project (C) refers to the overall endeavor, not a WBS element within it.

Topics

#WBS#work breakdown structure#decomposition#project planning

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice