nerdexam
ExamsPK0-004Questions#948
CompTIA

PK0-004 · Question #948

PK0-004 Question #948: Real Exam Question with Answer & Explanation

The correct answer is B: Task. A Work Breakdown Structure (WBS) decomposes the total project scope into manageable components. Tasks (B) are the work packages - the lowest-level deliverable elements in the WBS. Duration (D) is associated with each task to indicate how long each work package will take, supporti

Question

The project sponsor has asked a new project manager to create a WBS to present at the quarterly meeting with shareholders. Which of the following should be included in the WBS? (Choose two.)

Options

  • AProgram
  • BTask
  • CProject
  • DDuration
  • ECost variance
  • FStatement of work

Explanation

A Work Breakdown Structure (WBS) decomposes the total project scope into manageable components. Tasks (B) are the work packages - the lowest-level deliverable elements in the WBS. Duration (D) is associated with each task to indicate how long each work package will take, supporting schedule development. A Program (A) is a collection of related projects - not a WBS component. Cost variance (E) is a performance metric, not a WBS element. Statement of work (F) is a procurement/contract document. Project (C) refers to the overall endeavor, not a WBS element within it.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice