PK0-004 · Question #948
The project sponsor has asked a new project manager to create a WBS to present at the quarterly meeting with shareholders. Which of the following should be included in the WBS? (Choose two.)
The correct answer is B. Task D. Duration. A Work Breakdown Structure (WBS) decomposes the total project scope into manageable components. Tasks (B) are the work packages - the lowest-level deliverable elements in the WBS. Duration (D) is associated with each task to indicate how long each work package will take…
Question
The project sponsor has asked a new project manager to create a WBS to present at the quarterly meeting with shareholders. Which of the following should be included in the WBS? (Choose two.)
Options
- AProgram
- BTask
- CProject
- DDuration
- ECost variance
- FStatement of work
How the community answered
(42 responses)- A2% (1)
- B95% (40)
- C2% (1)
Explanation
A Work Breakdown Structure (WBS) decomposes the total project scope into manageable components. Tasks (B) are the work packages - the lowest-level deliverable elements in the WBS. Duration (D) is associated with each task to indicate how long each work package will take, supporting schedule development. A Program (A) is a collection of related projects - not a WBS component. Cost variance (E) is a performance metric, not a WBS element. Statement of work (F) is a procurement/contract document. Project (C) refers to the overall endeavor, not a WBS element within it.