PK0-004 · Question #949

A developer identifies a resolution to a minor issue the day before a product is scheduled to go live, but the fix will require additional work and testing. Which of the following is the BEST…

The correct answer is B. Log the resolution in the issue log, but resolve it after the product goes live. As the fix requires testing also after the additional work which may be time consuming. It may be better to log the issue in the issue log and resolve it after the product goes live.

Project management concepts

Question

A developer identifies a resolution to a minor issue the day before a product is scheduled to go live, but the fix will require additional work and testing. Which of the following is the BEST approach for the project?

Options

  • AMake the decision to push the fix before the product goes live.
  • BLog the resolution in the issue log, but resolve it after the product goes live.
  • CIgnore the fix because there is not enough time to implement it.
  • DHold an impromptu meeting with the CAB to fix the issue.

How the community answered

(17 responses)
  • A
    12% (2)
  • B
    76% (13)
  • C
    6% (1)
  • D
    6% (1)

Explanation

As the fix requires testing also after the additional work which may be time consuming. It may be better to log the issue in the issue log and resolve it after the product goes live.

Topics

#issue log#go-live#change management#risk