The project sponsor informs the project manager that additional functionality must be added. Which of the following is the FIRST constraint to be updated?
The correct answer is C. Scope. It is important to discuss the goal, budget and deliverables etc before including and additional function in a project.
Project management concepts
Question
The project sponsor informs the project manager that additional functionality must be added. Which of the following is the FIRST constraint to be updated?
Options
- ARequirements
- BResources
- CScope
- DSchedule
How the community answered
(68 responses)- A9% (6)
- B16% (11)
- C71% (48)
- D4% (3)
Explanation
It is important to discuss the goal, budget and deliverables etc before including and additional function in a project.
Topics
#triple constraint#scope management#requirements#change control