PK0-004 · Question #950
PK0-004 Question #950: Real Exam Question with Answer & Explanation
The correct answer is C: Scope. It is important to discuss the goal, budget and deliverables etc before including and additional function in a project.
Question
The project sponsor informs the project manager that additional functionality must be added. Which of the following is the FIRST constraint to be updated?
Options
- ARequirements
- BResources
- CScope
- DSchedule
Explanation
It is important to discuss the goal, budget and deliverables etc before including and additional function in a project.