The correct answer is C: Scope. It is important to discuss the goal, budget and deliverables etc before including and additional function in a project.

Question

The project sponsor informs the project manager that additional functionality must be added. Which of the following is the FIRST constraint to be updated?

Options

  • ARequirements
  • BResources
  • CScope
  • DSchedule

Explanation

It is important to discuss the goal, budget and deliverables etc before including and additional function in a project.