A project is created in response to a security breach. The project requires multiple patches to be fully compliant. Which of the following BEST describes this approach?
The correct answer is A. Agile. It's agile because agile is iterative and this requires multiple patches, i.e. multiple iterations.
Project life cycle phases
Question
A project is created in response to a security breach. The project requires multiple patches to be fully compliant. Which of the following BEST describes this approach?
Options
- AAgile
- BCritical path
- CSWOT
- DWaterfall
How the community answered
(27 responses)- A93% (25)
- B4% (1)
- C4% (1)
Explanation
It's agile because agile is iterative and this requires multiple patches, i.e. multiple iterations.