The correct answer is B: Evaluate the impact of the change.. The steps for the change control process: Identify and document, evaluate the impact, identify the approval authority.

Question

A customer requests an additional requirement for the finished product. After the change is identified and documented, which of the following would be the NEXT step in the process?

Options

  • AUpdate the project documents to show the change.
  • BEvaluate the impact of the change.
  • CImplement the requested change.
  • DSubmit the change request for approval.

Explanation

The steps for the change control process: Identify and document, evaluate the impact, identify the approval authority.