An urgent request is being submitted by senior leadership to align the project to new legislative requirements. Which of the following has the authority to approve the request?

The correct answer is B. Change control board. The Change Control Board (CCB) is the governing body with the authority to review, approve, reject, or defer changes to a project - regardless of who requests the change, including senior leadership. The CCB evaluates the impact of the change on scope, schedule, cost, and risk…

Project management concepts

Question

An urgent request is being submitted by senior leadership to align the project to new legislative requirements. Which of the following has the authority to approve the request?

Options

  • AProject management office
  • BChange control board
  • CProject manager
  • DFunctional manager

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    86% (18)
  • D
    10% (2)

Explanation

The Change Control Board (CCB) is the governing body with the authority to review, approve, reject, or defer changes to a project - regardless of who requests the change, including senior leadership. The CCB evaluates the impact of the change on scope, schedule, cost, and risk before approving. The Project Management Office (A) provides governance and standards but does not approve individual project changes. The project manager (C) may initiate or implement change requests but typically lacks unilateral approval authority. The functional manager (D) manages resources, not project change approval.

Topics

#change control board#change approval#governance#authority