A project manager is creating the WBS. In which of the following phases is the project?

The correct answer is B. Planning. The WBS is one of the key documents created at the end of the Planning phase.

Project life cycle phases

Question

A project manager is creating the WBS. In which of the following phases is the project?

Options

  • AInitiation
  • BPlanning
  • CExecution
  • DClosing

How the community answered

(36 responses)
  • A
    6% (2)
  • B
    89% (32)
  • C
    3% (1)
  • D
    3% (1)

Explanation

The WBS is one of the key documents created at the end of the Planning phase.

Topics

#WBS#planning phase#project planning#project life cycle