A project manager is creating the WBS. In which of the following phases is the project?
The correct answer is B. Planning. The WBS is one of the key documents created at the end of the Planning phase.
Project life cycle phases
Question
A project manager is creating the WBS. In which of the following phases is the project?
Options
- AInitiation
- BPlanning
- CExecution
- DClosing
How the community answered
(36 responses)- A6% (2)
- B89% (32)
- C3% (1)
- D3% (1)
Explanation
The WBS is one of the key documents created at the end of the Planning phase.