PK0-004 · Question #92
A project manger received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project…
The correct answer is B. Identify the approval authority. Based on CompTIA’s official exam objectives, the process should be: 1. Identify and document 2. Evaluate impact and justification 3. IDENTIFY APPROVAL AUTHORITY 4. Obtain approval 5. Implement change 6. Validate change/quality check 8. Communicate throughout as needed
Question
A project manger received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manger do NeXT?
Options
- AGain approval for the changes.
- BIdentify the approval authority
- CImplement the changes
- DCreate an emergency change request.
How the community answered
(43 responses)- A7% (3)
- B74% (32)
- C14% (6)
- D5% (2)
Explanation
Based on CompTIA’s official exam objectives, the process should be: 1. Identify and document 2. Evaluate impact and justification 3. IDENTIFY APPROVAL AUTHORITY 4. Obtain approval 5. Implement change 6. Validate change/quality check 8. Communicate throughout as needed