The correct answer is B: Identify the approval authority. Based on CompTIA’s official exam objectives, the process should be: 1. Identify and document 2. Evaluate impact and justification 3. IDENTIFY APPROVAL AUTHORITY 4. Obtain approval 5. Implement change 6. Validate change/quality check 8. Communicate throughout as needed

Question

A project manger received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manger do NeXT?

Options

  • AGain approval for the changes.
  • BIdentify the approval authority
  • CImplement the changes
  • DCreate an emergency change request.

Explanation

Based on CompTIA’s official exam objectives, the process should be: 1. Identify and document 2. Evaluate impact and justification 3. IDENTIFY APPROVAL AUTHORITY 4. Obtain approval 5. Implement change 6. Validate change/quality check 8. Communicate throughout as needed