The correct answer is A: Conduct a face-to-face or telephone meeting with the team member.. When a project manager has a quality concern about a specific team member's deliverable, direct one-on-one communication is the most effective and appropriate first step.

Question

A project manager is unsure if the quality of a deliverable from a SME meets specifications. Which of the following is the BEST way for the project manager to address the issue?

Options

  • AConduct a face-to-face or telephone meeting with the team member.
  • BSend an email outlining the concerns to the team member.
  • CSchedule a project team meeting to obtain feedback from everyone.
  • DPost the issue on the wiki page for input from stakeholders

Explanation

When a project manager has a quality concern about a specific team member's deliverable, direct one-on-one communication is the most effective and appropriate first step.

Common mistakes.

  • B. Email lacks the immediacy and interpersonal nuance needed for quality concerns, and tone can be misread, potentially damaging the working relationship.
  • C. Scheduling a full team meeting to address one person's deliverable quality is disproportionate, inefficient, and can embarrass the individual unnecessarily.
  • D. Posting an unresolved quality concern on a wiki exposes an internal issue prematurely to stakeholders before it has been discussed with the responsible party.

Concept tested. Project communication - appropriate channel selection

Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok