CompTIA
PK0-004 · Question #94
Which of the following are characteristics of a project? (Choose two.)
The correct answer is B. Temporary C. Start and finish. A project is temporary, meaning it has a start and a finish. An operation is ongoing, it will run for an indefinite amount of time.
Project management concepts
Question
Which of the following are characteristics of a project? (Choose two.)
Options
- AOngoing
- BTemporary
- CStart and finish
- DAchieving a goal
- EConsisting of milestones
- FRestricting the budget
How the community answered
(37 responses)- A3% (1)
- B86% (32)
- D3% (1)
- F8% (3)
Explanation
A project is temporary, meaning it has a start and a finish. An operation is ongoing, it will run for an indefinite amount of time.
Topics
#project definition#project characteristics#temporary endeavor
Community Discussion
No community discussion yet for this question.