Which of the following are characteristics of a project? (Choose two.)

The correct answer is B. Temporary C. Start and finish. A project is temporary, meaning it has a start and a finish. An operation is ongoing, it will run for an indefinite amount of time.

Project management concepts

Question

Which of the following are characteristics of a project? (Choose two.)

Options

  • AOngoing
  • BTemporary
  • CStart and finish
  • DAchieving a goal
  • EConsisting of milestones
  • FRestricting the budget

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    86% (32)
  • D
    3% (1)
  • F
    8% (3)

Explanation

A project is temporary, meaning it has a start and a finish. An operation is ongoing, it will run for an indefinite amount of time.

Topics

#project definition#project characteristics#temporary endeavor