A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule. Which of the following is the FIRST step the project take?
The correct answer is A. Assess the risk register's new items. The risk register is a list of risks that you can record in a simple spreadsheet that includes an identification number, risk name, risk description, risk owner, and response plan (or where the response plan can be located). This should be the first step, and then proceed…
Question
A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule. Which of the following is the FIRST step the project take?
Options
- AAssess the risk register's new items.
- BReview the task start and finish dates.
- CObtain additional resources
- DAnalyze the assigned hours.
How the community answered
(56 responses)- A71% (40)
- B18% (10)
- C4% (2)
- D7% (4)
Explanation
The risk register is a list of risks that you can record in a simple spreadsheet that includes an identification number, risk name, risk description, risk owner, and response plan (or where the response plan can be located). This should be the first step, and then proceed according to the plan specified in the risk register.