nerdexam
ExamsPK0-004Questions#96
CompTIA

PK0-004 · Question #96

PK0-004 Question #96: Real Exam Question with Answer & Explanation

The correct answer is A: forcing. When a project manager overrides both parties' ideas and unilaterally directs the team to use a third option, this is the 'forcing' conflict resolution technique.

Question

Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option. This type of conflict resolution is known as:

Options

  • Aforcing
  • Bavoiding.
  • Csmoothing.
  • Dcompromising.

Explanation

When a project manager overrides both parties' ideas and unilaterally directs the team to use a third option, this is the 'forcing' conflict resolution technique.

Common mistakes.

  • B. Avoiding means withdrawing from or postponing the conflict entirely without reaching any resolution, which is the opposite of what the PM does here.
  • C. Smoothing involves acknowledging the conflict but emphasizing areas of agreement to reduce tension, not overriding both parties with an external solution.
  • D. Compromising requires each party to give up something in order to reach a mutually acceptable middle ground, which does not occur here since neither party's approach is used.

Concept tested. Conflict resolution technique - forcing

Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice