A project team is performing change control on a project. During which of the following project activities does this normally occur?

The correct answer is C. Planning. Change control processes and the change management plan are formally established during Planning, where baselines and control mechanisms are defined before execution begins.

Project life cycle phases

Question

A project team is performing change control on a project. During which of the following project activities does this normally occur?

Options

  • AMonitoring
  • BExecution
  • CPlanning
  • DClosing

How the community answered

(22 responses)
  • A
    5% (1)
  • C
    95% (21)

Why each option

Change control processes and the change management plan are formally established during Planning, where baselines and control mechanisms are defined before execution begins.

AMonitoring

Monitoring is the phase where project performance is tracked against baselines; while variances may surface here, the formal change control process itself is defined earlier in Planning.

BExecution

Execution is where project work is carried out and change requests may be submitted, but the change control procedures that govern those requests were established in Planning.

CPlanningCorrect

During Planning, the project manager develops the change management plan, establishes the change control board, and defines thresholds and procedures that govern how changes will be evaluated and approved throughout the project. Creating these controls during Planning ensures baselines are set before work begins, giving the team a formal framework to manage deviations. Without this groundwork in Planning, change control during later phases would lack defined criteria and authority.

DClosing

Closing involves finalizing deliverables, obtaining acceptance, and archiving documents - introducing change control at this stage is outside the appropriate project lifecycle window.

Concept tested: Change control process establishment during Planning phase

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#change control#project phases#monitoring and controlling#change management

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice