PK0-004 · Question #917

PK0-004 Question #917: Real Exam Question with Answer & Explanation

The correct answer is C: Planning. Change control processes and the change management plan are formally established during Planning, where baselines and control mechanisms are defined before execution begins.

Question

A project team is performing change control on a project. During which of the following project activities does this normally occur?

Options

  • AMonitoring
  • BExecution
  • CPlanning
  • DClosing

Explanation

Change control processes and the change management plan are formally established during Planning, where baselines and control mechanisms are defined before execution begins.

Common mistakes.

  • A. Monitoring is the phase where project performance is tracked against baselines; while variances may surface here, the formal change control process itself is defined earlier in Planning.
  • B. Execution is where project work is carried out and change requests may be submitted, but the change control procedures that govern those requests were established in Planning.
  • D. Closing involves finalizing deliverables, obtaining acceptance, and archiving documents - introducing change control at this stage is outside the appropriate project lifecycle window.

Concept tested. Change control process establishment during Planning phase

Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok