PK0-004 · Question #916

Which of the following BEST describes a characteristic of a program?

The correct answer is D. It contains multiple components. A program is a group of related projects and activities managed in a coordinated way to achieve strategic benefits not available from managing them individually.

Project management concepts

Question

Which of the following BEST describes a characteristic of a program?

Options

  • AIt is temporary in nature.
  • BIt involves daily stand-up meetings.
  • CIt is part of a project.
  • DIt contains multiple components.

How the community answered

(22 responses)
  • A
    9% (2)
  • B
    5% (1)
  • D
    86% (19)

Why each option

A program is a group of related projects and activities managed in a coordinated way to achieve strategic benefits not available from managing them individually.

AIt is temporary in nature.

Being temporary in nature is a defining characteristic of a project, not a program - programs are ongoing governance structures that persist as long as their strategic goals require.

BIt involves daily stand-up meetings.

Daily stand-up meetings are a team-level Agile ceremony associated with individual projects, not a defining characteristic of a program.

CIt is part of a project.

A program is not part of a project; projects are components within a program, making this the reverse of the correct relationship.

DIt contains multiple components.Correct

By definition, a program contains multiple related projects and other work components governed together under a unified framework to achieve strategic objectives. Programs provide coordinated oversight across their components, enabling shared resources, risk management, and benefit realization that individual projects cannot achieve alone. This multi-component structure is the defining characteristic that distinguishes a program from a single project.

Concept tested: Program definition vs project - multi-component structure

Source: https://www.pmi.org/learning/library/program-management-standard-overview-8258