The project coordinator creates the following list to track the items team members are working on: Which of the following types of documents is shown in the table above?

The correct answer is C. Action item log. A list tracking tasks assigned to team members is an action item log, which records discrete work items, their owners, and completion status.

Tools and documentation

Question

The project coordinator creates the following list to track the items team members are working on:

Which of the following types of documents is shown in the table above?

Exhibits

PK0-004 question #843 exhibit 1
PK0-004 question #843 exhibit 2
PK0-004 question #843 exhibit 3

Options

  • AProject schedule
  • BProject charter
  • CAction item log
  • DWork breakdown structure

How the community answered

(50 responses)
  • A
    4% (2)
  • B
    2% (1)
  • C
    94% (47)

Why each option

A list tracking tasks assigned to team members is an action item log, which records discrete work items, their owners, and completion status.

AProject schedule

A project schedule is a time-based plan that shows task sequences, durations, dependencies, and milestones - it is a more comprehensive planning artifact than a simple tracking list.

BProject charter

A project charter is a high-level authorization document that defines project objectives, scope, and the project manager's authority - it does not track individual team member work items.

CAction item logCorrect

An action item log is a project document used to capture and track specific tasks assigned to team members, including the owner, due date, and current status of each item. It is designed for ongoing operational tracking of work in progress, which matches the project coordinator's described list exactly. Unlike a project schedule, it focuses on discrete action items rather than a sequenced delivery timeline.

DWork breakdown structure

A work breakdown structure is a hierarchical decomposition of project deliverables into manageable components and does not track who is working on specific tasks or their current status.

Concept tested: Action item log vs. other project tracking documents

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#action item log#project tracking#document identification#team coordination