Ann, a project sponsor, is concerned by how long issues remain open before being brought to her attention. Which of the following would be BEST way for the project manager to increase Ann's…
The correct answer is A. Tailor the status reports to bring only certain information forward. Highlighting only certain important issues shall enable Ann to keep an eye on important issues.
Project management concepts
Question
Ann, a project sponsor, is concerned by how long issues remain open before being brought to her attention. Which of the following would be BEST way for the project manager to increase Ann's visibility on issues?
Options
- ATailor the status reports to bring only certain information forward.
- BProvide more detail in the regular status reports.
- CSchedule daily, face-to-face meetings with Ann.
- DIncrease the frequency of the status reports.
How the community answered
(20 responses)- A75% (15)
- B5% (1)
- C15% (3)
- D5% (1)
Explanation
Highlighting only certain important issues shall enable Ann to keep an eye on important issues.