Which of the following project documents should be used to record the occurrence of an unplanned event?

The correct answer is D. Issue log. An issue log is the correct document for recording unplanned events that have already occurred and require active tracking and resolution.

Tools and documentation

Question

Which of the following project documents should be used to record the occurrence of an unplanned event?

Options

  • AAction log
  • BRisk log
  • CChange log
  • DIssue log

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    3% (1)
  • D
    88% (30)

Why each option

An issue log is the correct document for recording unplanned events that have already occurred and require active tracking and resolution.

AAction log

An action log tracks tasks and follow-up items assigned to team members, not the occurrence of unplanned events or problems.

BRisk log

A risk log records identified potential future threats or opportunities and their response plans, not events that have already occurred.

CChange log

A change log documents approved or requested changes to project scope, schedule, or cost baselines, not unplanned events that arise during execution.

DIssue logCorrect

An issue log (also called an issue register) is specifically designed to capture unplanned events or problems that have materialized during the project, documenting their description, owner, priority, and resolution status so they can be actively managed and resolved.

Concept tested: Issue log for recording unplanned project events

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#issue log#project documentation#unplanned events#logs and registers

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice