A project manager noticed the development team supporting a project does not have sufficient skills to complete the development phase. The project manager has discussed this issue with the…

The correct answer is A. Accepting. When a project manager acknowledges a risk and decides to proceed without taking action to change its probability or impact, the strategy being applied is acceptance.

Project management concepts

Question

A project manager noticed the development team supporting a project does not have sufficient skills to complete the development phase. The project manager has discussed this issue with the functional manager and agreed to continue with the development phase due to time restrictions. Which of the following strategies is the project manager applying?

Options

  • AAccepting
  • BMitigating
  • CAvoiding
  • DTransferring

How the community answered

(25 responses)
  • A
    80% (20)
  • B
    4% (1)
  • C
    8% (2)
  • D
    8% (2)

Why each option

When a project manager acknowledges a risk and decides to proceed without taking action to change its probability or impact, the strategy being applied is acceptance.

AAcceptingCorrect

Risk acceptance means the project team acknowledges the existence of a risk and deliberately chooses not to change the project plan to deal with it, often because the cost or effort of other responses outweighs the benefit - in this case, the time restriction makes other strategies impractical so the team proceeds knowing the skill gap exists.

BMitigating

Mitigating involves taking proactive steps to reduce the probability or impact of a risk, such as providing training to the team to address the skill gap, which is not what occurred here.

CAvoiding

Avoiding involves changing the project plan to eliminate the risk entirely, such as delaying the development phase until skilled resources are available, which contradicts the decision to continue due to time restrictions.

DTransferring

Transferring shifts the financial or operational impact of the risk to a third party, such as outsourcing development to a skilled vendor, which was not the agreed-upon course of action.

Concept tested: Risk acceptance strategy in project management

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#risk acceptance#risk strategies#risk response#resource constraints

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice