nerdexam
CompTIA

PK0-004 · Question #84

Which of the following describes a burn rate?

The correct answer is C. The rate at which the project budget is used. Burn rate is a project management metric that measures how quickly the project budget is being spent over time.

Project management concepts

Question

Which of the following describes a burn rate?

Options

  • AThe rate at which project documents are disposed
  • BThe rate at which project personnel leave the project
  • CThe rate at which the project budget is used
  • DThe rate at which the timeline increases

How the community answered

(43 responses)
  • A
    2% (1)
  • B
    7% (3)
  • C
    86% (37)
  • D
    5% (2)

Why each option

Burn rate is a project management metric that measures how quickly the project budget is being spent over time.

AThe rate at which project documents are disposed

Disposal of project documents is governed by records management policies, not burn rate.

BThe rate at which project personnel leave the project

The rate at which personnel leave a project is referred to as attrition or staff turnover, not burn rate.

CThe rate at which the project budget is usedCorrect

Burn rate specifically refers to the speed at which a project consumes its allocated budget, typically expressed as cost per unit of time. It is used to monitor spending velocity and forecast whether remaining funds will be sufficient to complete the project. A high burn rate relative to progress signals potential budget overrun.

DThe rate at which the timeline increases

An increasing timeline refers to schedule slippage or schedule variance, which is a separate metric from budget consumption.

Concept tested: Project budget burn rate definition

Source: https://www.pmi.org/learning/library/budget-burn-rate-project-control-6355

Topics

#burn rate#budget consumption#cost management

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice