The correct answer is C: Project sponsor. Milestones completion must be communicated to project sponsor and porject stakeholders.

Question

A milestone task on the critical path has been completed. Which of the following should the project manger notify?

Options

  • AOwner of predecessor task
  • BProject team
  • CProject sponsor
  • DProject steering committee

Explanation

Milestones completion must be communicated to project sponsor and porject stakeholders.