CompTIA
PK0-004 · Question #85
A milestone task on the critical path has been completed. Which of the following should the project manger notify?
The correct answer is C. Project sponsor. Milestones completion must be communicated to project sponsor and porject stakeholders.
Project management concepts
Question
A milestone task on the critical path has been completed. Which of the following should the project manger notify?
Options
- AOwner of predecessor task
- BProject team
- CProject sponsor
- DProject steering committee
How the community answered
(42 responses)- A2% (1)
- B5% (2)
- C88% (37)
- D5% (2)
Explanation
Milestones completion must be communicated to project sponsor and porject stakeholders.
Topics
#milestone completion#critical path#stakeholder notification#project sponsor
Community Discussion
No community discussion yet for this question.