PK0-004 · Question #85
PK0-004 Question #85: Real Exam Question with Answer & Explanation
The correct answer is C: Project sponsor. Milestones completion must be communicated to project sponsor and porject stakeholders.
Question
A milestone task on the critical path has been completed. Which of the following should the project manger notify?
Options
- AOwner of predecessor task
- BProject team
- CProject sponsor
- DProject steering committee
Explanation
Milestones completion must be communicated to project sponsor and porject stakeholders.