nerdexam
CompTIA

PK0-004 · Question #81

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

The correct answer is A. SCRUM retrospective. In iterative frameworks like Scrum, a retrospective is held at the end of each iteration (sprint) to inspect and improve the team's process.

Project life cycle phases

Question

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

Options

  • ASCRUM retrospective
  • BKickoff meeting
  • CBudget baseline
  • DRisk review

How the community answered

(41 responses)
  • A
    90% (37)
  • B
    5% (2)
  • C
    2% (1)
  • D
    2% (1)

Why each option

In iterative frameworks like Scrum, a retrospective is held at the end of each iteration (sprint) to inspect and improve the team's process.

ASCRUM retrospectiveCorrect

A Scrum retrospective is a formal ceremony conducted at the end of every sprint where the team reflects on what went well, what did not, and what process improvements to implement in the next iteration, making it a defining characteristic of the iterative approach.

BKickoff meeting

A kickoff meeting occurs once at the start of a project or phase to align stakeholders on objectives, not at the end of each iteration.

CBudget baseline

A budget baseline is established during project planning as a fixed reference point for cost performance measurement, not an activity repeated each iteration.

DRisk review

A risk review can occur at various points in a project lifecycle but is not a defined end-of-iteration ceremony specific to iterative frameworks like Scrum.

Concept tested: Scrum retrospective ceremony in iterative frameworks

Source: https://scrumguides.org/scrum-guide.html#sprint-retrospective

Topics

#iterative approach#SCRUM retrospective#agile methodology#iteration review

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice