PK0-004 · Question #80
A WBS is being developed for a project. Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
The correct answer is A. Project team members. Project team members contribute project expertise and deliverables according to the project schedule. They provide estimations of task duration, costs, and dependencies.
Tools and documentation
Question
A WBS is being developed for a project. Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
Options
- AProject team members
- BProject sponsor
- CProject manager
- DProject scheduler
How the community answered
(45 responses)- A89% (40)
- B2% (1)
- C7% (3)
- D2% (1)
Explanation
Project team members contribute project expertise and deliverables according to the project schedule. They provide estimations of task duration, costs, and dependencies.
Topics
#WBS#cost and time estimation#team member involvement#project planning