nerdexam
CompTIA

PK0-004 · Question #79

After identifying all known tasks, the project manager has started to sequence and set durations Which of the following describes how the project manager should BEST determine the initial sequence…

The correct answer is A. Use milestones identified in the project charter. Milestones act as major events that can be used to determine the sequencing and durations between milestones.

Project life cycle phases

Question

After identifying all known tasks, the project manager has started to sequence and set durations Which of the following describes how the project manager should BEST determine the initial sequence and durations?

Options

  • AUse milestones identified in the project charter.
  • BUse data based on past knowledge.
  • CHold a full team workshop to review the complete WBS.
  • DCollaborate with other project managers.

How the community answered

(18 responses)
  • A
    78% (14)
  • B
    11% (2)
  • C
    6% (1)
  • D
    6% (1)

Explanation

Milestones act as major events that can be used to determine the sequencing and durations between milestones.

Topics

#activity sequencing#project charter milestones#WBS#schedule planning

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice