CompTIA
PK0-004 · Question #79
PK0-004 Question #79: Real Exam Question with Answer & Explanation
The correct answer is A: Use milestones identified in the project charter.. Milestones act as major events that can be used to determine the sequencing and durations between milestones.
Question
After identifying all known tasks, the project manager has started to sequence and set durations Which of the following describes how the project manager should BEST determine the initial sequence and durations?
Options
- AUse milestones identified in the project charter.
- BUse data based on past knowledge.
- CHold a full team workshop to review the complete WBS.
- DCollaborate with other project managers.
Explanation
Milestones act as major events that can be used to determine the sequencing and durations between milestones.
Community Discussion
No community discussion yet for this question.