PK0-004 · Question #79
After identifying all known tasks, the project manager has started to sequence and set durations Which of the following describes how the project manager should BEST determine the initial sequence…
The correct answer is A. Use milestones identified in the project charter. Milestones act as major events that can be used to determine the sequencing and durations between milestones.
Project life cycle phases
Question
After identifying all known tasks, the project manager has started to sequence and set durations Which of the following describes how the project manager should BEST determine the initial sequence and durations?
Options
- AUse milestones identified in the project charter.
- BUse data based on past knowledge.
- CHold a full team workshop to review the complete WBS.
- DCollaborate with other project managers.
How the community answered
(18 responses)- A78% (14)
- B11% (2)
- C6% (1)
- D6% (1)
Explanation
Milestones act as major events that can be used to determine the sequencing and durations between milestones.
Topics
#activity sequencing#project charter milestones#WBS#schedule planning