CompTIA
PK0-004 · Question #809
Which of the following is the BEST time to establish the project cost baseline?
The correct answer is C. Before the project charter is signed. It is a best practice to set the baseline of the schedule Before the project charter is signed.
Project life cycle phases
Question
Which of the following is the BEST time to establish the project cost baseline?
Options
- AAfter the WBS is created
- BDuring sprint planning
- CBefore the project charter is signed
- DDuring the project kickoff meeting
How the community answered
(44 responses)- A5% (2)
- B2% (1)
- C82% (36)
- D11% (5)
Explanation
It is a best practice to set the baseline of the schedule Before the project charter is signed.
Topics
#cost baseline#project planning#WBS#project charter
Community Discussion
No community discussion yet for this question.