CompTIA
PK0-004 · Question #809
PK0-004 Question #809: Real Exam Question with Answer & Explanation
The correct answer is C: Before the project charter is signed. It is a best practice to set the baseline of the schedule Before the project charter is signed.
Question
Which of the following is the BEST time to establish the project cost baseline?
Options
- AAfter the WBS is created
- BDuring sprint planning
- CBefore the project charter is signed
- DDuring the project kickoff meeting
Explanation
It is a best practice to set the baseline of the schedule Before the project charter is signed.
Community Discussion
No community discussion yet for this question.