A project has come to a close, and the project manager is evaluating each team member. After completing the evaluations, the results are emailed to the supervisor and used for yearly evaluations…
The correct answer is A. Strong matrix. The project manager is the one doing the evaluation of the members which means he has strong
Project management concepts
Question
A project has come to a close, and the project manager is evaluating each team member. After completing the evaluations, the results are emailed to the supervisor and used for yearly evaluations. Which of the following organizational types is being described?
Options
- AStrong matrix
- BVertical
- CProjectized
- DFunctional
How the community answered
(35 responses)- A74% (26)
- B3% (1)
- C9% (3)
- D14% (5)
Explanation
The project manager is the one doing the evaluation of the members which means he has strong