A project has come to a close, and the project manager is evaluating each team member. After completing the evaluations, the results are emailed to the supervisor and used for yearly evaluations…

The correct answer is A. Strong matrix. The project manager is the one doing the evaluation of the members which means he has strong

Project management concepts

Question

A project has come to a close, and the project manager is evaluating each team member. After completing the evaluations, the results are emailed to the supervisor and used for yearly evaluations. Which of the following organizational types is being described?

Options

  • AStrong matrix
  • BVertical
  • CProjectized
  • DFunctional

How the community answered

(35 responses)
  • A
    74% (26)
  • B
    3% (1)
  • C
    9% (3)
  • D
    14% (5)

Explanation

The project manager is the one doing the evaluation of the members which means he has strong

Topics

#strong matrix#organizational structure#performance evaluation#functional manager