A customer added an additional requirement for a product being developed. Which of the following should the project manager do FIRST?
The correct answer is B. Evaluate the change with the project team. Evaluation of the change in necessary to avoid any constrains on budget.
Project life cycle phases
Question
A customer added an additional requirement for a product being developed. Which of the following should the project manager do FIRST?
Options
- APresent the change request to the CAB.
- BEvaluate the change with the project team.
- CSet up a face-to-face meeting with the project sponsor
- DOrganize a steering committee meeting.
How the community answered
(39 responses)- A3% (1)
- B79% (31)
- C13% (5)
- D5% (2)
Explanation
Evaluation of the change in necessary to avoid any constrains on budget.