PK0-004 · Question #703
A project sponsor would like the status of a key deliverable at the first project milestone. Which of the following is a characteristic of a milestone?
The correct answer is D. Zero duration. Milestones are typically major accomplishments of the project and mark the completion of major deliverables or some other key event in the project. For example, approval and sign-off on project deliverables might be considered milestones. Other examples might be the completion…
Question
A project sponsor would like the status of a key deliverable at the first project milestone. Which of the following is a characteristic of a milestone?
Options
- AOngoing
- BResource assigned
- CHigh cost
- DZero duration
How the community answered
(34 responses)- A3% (1)
- C6% (2)
- D91% (31)
Explanation
Milestones are typically major accomplishments of the project and mark the completion of major deliverables or some other key event in the project. For example, approval and sign-off on project deliverables might be considered milestones. Other examples might be the completion of a prototype, functional testing, contract approval, and so on. A milestone is typically denoted on a project schedule as an event that is achieved once all the deliverables associated with that milestone are completed and it has a duration of zero.
Topics