A project manager and a project sponsor have agreed to accept all risks that have a low impact and low probability. Given the information below: Which of the following risks from the risk register…
The correct answer is B. 2 F. 6. Risk ID 4 is closed, lowest risks are 2 and 6.
Project management concepts
Question
A project manager and a project sponsor have agreed to accept all risks that have a low impact and low probability. Given the information below:
Which of the following risks from the risk register should have an acceptance strategy? (Choose two.)
Exhibits
Options
- A1
- B2
- C3
- D4
- E5
- F6
How the community answered
(47 responses)- A13% (6)
- B55% (26)
- C6% (3)
- D23% (11)
- E2% (1)
Explanation
Risk ID 4 is closed, lowest risks are 2 and 6.
Topics
#risk register#risk acceptance#risk probability#risk impact