PK0-004 · Question #702

A project manager and a project sponsor have agreed to accept all risks that have a low impact and low probability. Given the information below: Which of the following risks from the risk register…

The correct answer is B. 2 F. 6. Risk ID 4 is closed, lowest risks are 2 and 6.

Project management concepts

Question

A project manager and a project sponsor have agreed to accept all risks that have a low impact and low probability. Given the information below:

Which of the following risks from the risk register should have an acceptance strategy? (Choose two.)

Exhibits

PK0-004 question #702 exhibit 1
PK0-004 question #702 exhibit 2
PK0-004 question #702 exhibit 3

Options

  • A1
  • B2
  • C3
  • D4
  • E5
  • F6

How the community answered

(47 responses)
  • A
    13% (6)
  • B
    55% (26)
  • C
    6% (3)
  • D
    23% (11)
  • E
    2% (1)

Explanation

Risk ID 4 is closed, lowest risks are 2 and 6.

Topics

#risk register#risk acceptance#risk probability#risk impact