After accepting and assigning a positive risk, risk owners have a responsibility to:

The correct answer is A. maximize the probability. It's a positive risk so you want to maximize the probability.

Project management concepts

Question

After accepting and assigning a positive risk, risk owners have a responsibility to:

Options

  • Amaximize the probability.
  • Bupdate the risk register.
  • Cminimize the impact.
  • Ddetermine a mitigation strategy.

How the community answered

(40 responses)
  • A
    90% (36)
  • B
    5% (2)
  • C
    3% (1)
  • D
    3% (1)

Explanation

It's a positive risk so you want to maximize the probability.