PK0-004 · Question #704
After accepting and assigning a positive risk, risk owners have a responsibility to:
The correct answer is A. maximize the probability. It's a positive risk so you want to maximize the probability.
Project management concepts
Question
After accepting and assigning a positive risk, risk owners have a responsibility to:
Options
- Amaximize the probability.
- Bupdate the risk register.
- Cminimize the impact.
- Ddetermine a mitigation strategy.
How the community answered
(40 responses)- A90% (36)
- B5% (2)
- C3% (1)
- D3% (1)
Explanation
It's a positive risk so you want to maximize the probability.
Topics
#positive risk#risk ownership#risk acceptance#risk strategy
Community Discussion
No community discussion yet for this question.