A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close-date. The project…
The correct answer is C. Network diagram D. Project schedule. Network diagram: A depiction of project activities and the interrelationships between these
Tools and documentation
Question
A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close-date. The project team meets and determines that the project should be fast-tracked. Which of the following documents should the project team reference to fast-track the project? (Choose two.).
Options
- AScope management plan
- BConfiguration management plan
- CNetwork diagram
- DProject schedule
- EProject plan
How the community answered
(28 responses)- A18% (5)
- B4% (1)
- C71% (20)
- E7% (2)
Explanation
Network diagram: A depiction of project activities and the interrelationships between these
Topics
#fast-tracking#network diagram#project schedule#schedule compression