PK0-004 · Question #7

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close-date. The project…

The correct answer is C. Network diagram D. Project schedule. Network diagram: A depiction of project activities and the interrelationships between these

Tools and documentation

Question

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close-date. The project team meets and determines that the project should be fast-tracked. Which of the following documents should the project team reference to fast-track the project? (Choose two.).

Options

  • AScope management plan
  • BConfiguration management plan
  • CNetwork diagram
  • DProject schedule
  • EProject plan

How the community answered

(28 responses)
  • A
    18% (5)
  • B
    4% (1)
  • C
    71% (20)
  • E
    7% (2)

Explanation

Network diagram: A depiction of project activities and the interrelationships between these

Topics

#fast-tracking#network diagram#project schedule#schedule compression