PK0-004 · Question #8
During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor's tasks The project team has just informed the project manager their…
The correct answer is A. During the planning phase, the project manager should have recognized the relationship. The question asks what should have been done to prevent this from happening. So the project manager should have recognized that the project team's task were directly related to the vendor's during the planning phase. Recognizing this during planning will avoid this schedule…
Question
During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor's tasks The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months. Which of the following should have occurred to prevent this issue?
Options
- ADuring the planning phase, the project manager should have recognized the relationship
- BThe project manager should have crashed the schedule for the vendor to keep it at the same
- CDuring the project team's regular status meeting with the vendor, the project team should
- DDuring the project team's regular status meeting with the vendor, the vendor should have
How the community answered
(39 responses)- A85% (33)
- B5% (2)
- C8% (3)
- D3% (1)
Explanation
The question asks what should have been done to prevent this from happening. So the project manager should have recognized that the project team's task were directly related to the vendor's during the planning phase. Recognizing this during planning will avoid this schedule mismatch and prevent it from happening on the next project.