PK0-004 · Question #8
PK0-004 Question #8: Real Exam Question with Answer & Explanation
The correct answer is A: During the planning phase, the project manager should have recognized the relationship. The question asks what should have been done to prevent this from happening. So the project manager should have recognized that the project team's task were directly related to the vendor's during the planning phase. Recognizing this during planning will avoid this schedule misma
Question
Options
- ADuring the planning phase, the project manager should have recognized the relationship
- BThe project manager should have crashed the schedule for the vendor to keep it at the same
- CDuring the project team's regular status meeting with the vendor, the project team should
- DDuring the project team's regular status meeting with the vendor, the vendor should have
Explanation
The question asks what should have been done to prevent this from happening. So the project manager should have recognized that the project team's task were directly related to the vendor's during the planning phase. Recognizing this during planning will avoid this schedule mismatch and prevent it from happening on the next project.
Community Discussion
No community discussion yet for this question.