During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. Which of the following documents would contain these items?

The correct answer is A. Business case. A business case provides justification for undertaking a project, programme or portfolio. It evaluates the benefit, cost and risk of alternative options and provides a rationale for the preferred solution.

Project life cycle phases

Question

During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. Which of the following documents would contain these items?

Options

  • ABusiness case
  • BRequirements document
  • CProject timeline
  • DTask plan

How the community answered

(50 responses)
  • A
    88% (44)
  • B
    2% (1)
  • C
    4% (2)
  • D
    6% (3)

Explanation

A business case provides justification for undertaking a project, programme or portfolio. It evaluates the benefit, cost and risk of alternative options and provides a rationale for the preferred solution.

Topics