PK0-004 · Question #6

PK0-004 Question #6: Real Exam Question with Answer & Explanation

The correct answer is A: Business case. A business case provides justification for undertaking a project, programme or portfolio. It evaluates the benefit, cost and risk of alternative options and provides a rationale for the preferred solution.

Question

During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. Which of the following documents would contain these items?

Options

  • ABusiness case
  • BRequirements document
  • CProject timeline
  • DTask plan

Explanation

A business case provides justification for undertaking a project, programme or portfolio. It evaluates the benefit, cost and risk of alternative options and provides a rationale for the preferred solution.