PK0-004 · Question #5
Which of the following documents should be used to provide high-level reporting to key stakeholders?
The correct answer is A. Dashboard. Dashboard - Once the project enters the Executing phase, you should conduct regular status meetings that are supplemented with dashboard reports and status reports. Dashboards are a way to visually depict the progress of the project and are often used by executives in the…
Question
Which of the following documents should be used to provide high-level reporting to key stakeholders?
Options
- ADashboard
- BCommunication plan
- CStatement of work
- DProject charter
How the community answered
(24 responses)- A88% (21)
- B4% (1)
- C8% (2)
Explanation
Dashboard - Once the project enters the Executing phase, you should conduct regular status meetings that are supplemented with dashboard reports and status reports. Dashboards are a way to visually depict the progress of the project and are often used by executives in the organization. They are easy to read and are usually updated with real-time information so they are always up to date.