A project manager is overseeing a project to analyze large amounts of data to find customer preferences. The large data sets are hosted by an external provider, and the project manager is concerned…

The correct answer is B. Risk register. The concern about potentially losing access is a future uncertainty - a risk, not a current problem. The risk register is the correct document because it captures identified risks, their probability, potential impact, and planned responses. An issue log documents problems that…

Tools and documentation

Question

A project manager is overseeing a project to analyze large amounts of data to find customer preferences. The large data sets are hosted by an external provider, and the project manager is concerned about losing access to the data. Which of the following documents is appropriate for use in this situation?

Options

  • AProject schedule
  • BRisk register
  • CAction item log
  • DIssue log

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    87% (26)
  • C
    3% (1)
  • D
    7% (2)

Explanation

The concern about potentially losing access is a future uncertainty - a risk, not a current problem. The risk register is the correct document because it captures identified risks, their probability, potential impact, and planned responses. An issue log documents problems that have already occurred. An action item log tracks specific tasks assigned to team members. The project schedule tracks timelines and milestones. Since losing access to the external data has not happened yet but could happen, it belongs in the risk register as an identified threat requiring a mitigation or contingency plan.