PK0-004 · Question #679
Which of the following activities is MOST likely to be completed in the closing project phase?
The correct answer is A. Operational training. The closing phase focuses on formally completing the project and transitioning deliverables to the operational team. Operational training - teaching end-users or support staff how to use or maintain the deliverable - happens at handoff and is a core closing activity. Testing…
Question
Which of the following activities is MOST likely to be completed in the closing project phase?
Options
- AOperational training
- BTesting deliverables
- CUpdating the scope statement
- DPerforming a final quality check
How the community answered
(28 responses)- A93% (26)
- B4% (1)
- C4% (1)
Explanation
The closing phase focuses on formally completing the project and transitioning deliverables to the operational team. Operational training - teaching end-users or support staff how to use or maintain the deliverable - happens at handoff and is a core closing activity. Testing deliverables occurs during execution or monitoring/controlling. Updating the scope statement is a planning or change-control activity done mid-project. A final quality check is a monitoring/controlling activity that occurs before closing, not during it. Only operational training fits the closing phase's purpose of knowledge transfer and transition.
Topics
Community Discussion