nerdexam
CompTIA

PK0-004 · Question #663

A customer-requested project change has been approved, implemented, and validated. Which of the following should the project manager do NEXT?

The correct answer is D. Update the project management. Once a change is approved, implemented, and validated, the project baseline and planning documents must be updated to reflect the new state of the project. Updating the project management plan (which includes the scope baseline, schedule baseline, cost baseline, and subsidiary…

Project life cycle phases

Question

A customer-requested project change has been approved, implemented, and validated. Which of the following should the project manager do NEXT?

Options

  • AUpdate the project charter.
  • BUpdate the statement of work.
  • CUpdate the lessons learned.
  • DUpdate the project management

How the community answered

(27 responses)
  • A
    11% (3)
  • C
    7% (2)
  • D
    81% (22)

Explanation

Once a change is approved, implemented, and validated, the project baseline and planning documents must be updated to reflect the new state of the project. Updating the project management plan (which includes the scope baseline, schedule baseline, cost baseline, and subsidiary plans) ensures the plan remains the authoritative reference going forward. The project charter (A) is a high-level initiating document not revised for individual changes. The statement of work (B) is typically a contract artifact. Lessons learned (C) are captured continuously or at close-out, but they are not the immediate next step after a change is validated.

Topics

#change control#project management plan#change implementation#integrated change control

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice