A project manager arrives at a worksite and finds the installation team performing unapproved work. The installation team claims the sponsor verbally requested the work, as it was necessary for the…
The correct answer is A. Scope creep. Scope creep involves changing the project or product scope without having approval to do so and without considering the impacts that will have on the project schedule, budget, and resources.
Project management concepts
Question
A project manager arrives at a worksite and finds the installation team performing unapproved work. The installation team claims the sponsor verbally requested the work, as it was necessary for the project. Which of the following has MOST likely occurred?
Options
- AScope creep
- BGold plating
- CTask reprioritization
- DLack of requirements
How the community answered
(57 responses)- A95% (54)
- B4% (2)
- C2% (1)
Explanation
Scope creep involves changing the project or product scope without having approval to do so and without considering the impacts that will have on the project schedule, budget, and resources.