PK0-004 · Question #665

In a highway construction project, the project team has identified the need to utilize additional land for staging equipment. After documenting the change request, which of the following should be…

The correct answer is D. Identify the approval authority. The integrated change control process follows a defined sequence: document the change request, then determine who has the authority to approve it before submitting it for review. Identifying the approval authority (D) must come before obtaining approval (C), because you cannot…

Project life cycle phases

Question

In a highway construction project, the project team has identified the need to utilize additional land for staging equipment. After documenting the change request, which of the following should be accomplished NEXT?

Options

  • ACommunicate with the stakeholders
  • BAudit the documentation
  • CObtain approval
  • DIdentify the approval authority

How the community answered

(44 responses)
  • A
    16% (7)
  • B
    9% (4)
  • C
    2% (1)
  • D
    73% (32)

Explanation

The integrated change control process follows a defined sequence: document the change request, then determine who has the authority to approve it before submitting it for review. Identifying the approval authority (D) must come before obtaining approval (C), because you cannot route the request correctly without knowing who must sign off. Land acquisition in a government or infrastructure project may involve multiple authorities (government agencies, sponsors, legal). Communicating with stakeholders (A) and auditing documentation (B) are valid activities but are not the immediate next step in the change control workflow.

Topics

#change control process#approval authority#change request#scope change