PK0-004 · Question #661
Due to an overabundance of project issues reported at status meetings, a project manager wants to purchase a ticketing system to help manage the issues and impacts to the project. Which of the…
The correct answer is B. KPIs. A ticketing system tracks and reports on project issues-volume, severity, resolution time, trends, and status. This data represents Key Performance Indicators (KPIs), which are measurable metrics used to evaluate project health and performance. The other options are unrelated…
Question
Due to an overabundance of project issues reported at status meetings, a project manager wants to purchase a ticketing system to help manage the issues and impacts to the project. Which of the following describes the information the new ticketing system would provide?
Options
- ARTM
- BKPIs
- CBAC
- DETC
How the community answered
(29 responses)- A7% (2)
- B86% (25)
- C3% (1)
- D3% (1)
Explanation
A ticketing system tracks and reports on project issues-volume, severity, resolution time, trends, and status. This data represents Key Performance Indicators (KPIs), which are measurable metrics used to evaluate project health and performance. The other options are unrelated: an RTM (Requirements Traceability Matrix) maps requirements to deliverables; BAC (Budget at Completion) is the total planned project budget; and ETC (Estimate to Complete) forecasts remaining cost. None of those are outputs of an issue ticketing system.
Topics
Community Discussion
No community discussion yet for this question.