PK0-004 · Question #660

A project manager is reviewing a project's status and finds that while it is 25% under budget, there are significant quality defects, and the project is behind by six weeks. Which of the following…

The correct answer is A. Resources. Resources on a project schedule typically refer to human resources and/or consulting or contracting resources who will work on the tasks.

Project management concepts

Question

A project manager is reviewing a project’s status and finds that while it is 25% under budget, there are significant quality defects, and the project is behind by six weeks. Which of the following should the project manager increase to BEST resolve this issue?

Options

  • AResources
  • BQuality
  • CSchedule
  • DScope

How the community answered

(48 responses)
  • A
    73% (35)
  • B
    6% (3)
  • C
    17% (8)
  • D
    4% (2)

Explanation

Resources on a project schedule typically refer to human resources and/or consulting or contracting resources who will work on the tasks.

Topics

#resource management#triple constraint#quality management#schedule management