A project manager is reviewing a project's status and finds that while it is 25% under budget, there are significant quality defects, and the project is behind by six weeks. Which of the following…
The correct answer is A. Resources. Resources on a project schedule typically refer to human resources and/or consulting or contracting resources who will work on the tasks.
Project management concepts
Question
A project manager is reviewing a project’s status and finds that while it is 25% under budget, there are significant quality defects, and the project is behind by six weeks. Which of the following should the project manager increase to BEST resolve this issue?
Options
- AResources
- BQuality
- CSchedule
- DScope
How the community answered
(48 responses)- A73% (35)
- B6% (3)
- C17% (8)
- D4% (2)
Explanation
Resources on a project schedule typically refer to human resources and/or consulting or contracting resources who will work on the tasks.
Topics
#resource management#triple constraint#quality management#schedule management